Rate Analysis of Concrete – Explanation
Overhead & Profit. 1. Estimation of Materials. Assume We need 1 m3 of wet volume concrete of M25 Mix, (Mix Ratio, M25 = 1: 1 : 2) So Total Parts = 1+1+2 = 4 Parts which …
اقرأ أكثرDetailed Specification Of Reinforced Cement Concrete or RCC …
Here are the step by step detailed specifications of reinforced cement concrete (RCC)-. 1- Cement Materials. In the reinforced cement concrete (RCC) the cement is fresh portland cement of grade 33 and the cement takes according to I.S. 269 specifications. 2- Coarse Aggregate Materials.
اقرأ أكثرRate Analysis of Concrete – Explanation
Overhead & Profit. 1. Estimation of Materials. Assume We need 1 m3 of wet volume concrete of M25 Mix, (Mix Ratio, M25 = 1: 1 : 2) So Total Parts = 1+1+2 = 4 Parts which gives Dry volume that means before adding …
اقرأ أكثرWater Tank Material Calculation | RCC Water Tank Estimate
Material Estimate of the RCC circular water tank Diagram representation for section/side view - RCC water tank is circular. Plain cement concrete = 1:2:4 with thickness = 10 cm. RCC = 1:2:4 with thickness = 10 cm. Opening for water tank is 60 cm with thickness = 10 cm. Thickness of RCC walls = 15 cm. 1% of 4M bars is used in wall.
اقرأ أكثرRCC cost per cubic feet/ per sq ft/ per cubic meter
Since 1000 sq ft is equal to 9.42 cubic meters. So the cost of RCC per cubic meter = 210570 ÷ 9.42 = 22353. The RCC cost per cubic meter is approx 22353 INR. This cost includes steel, cement, sand, aggregate, shuttering, labor, and machinery cost. This cost is not the fixed cost of RCC.
اقرأ أكثرRate analysis for Concrete- Step by Step calculation …
Step -1 Write all the known values of the materials. Here we should know that, Total Concrete = 10 m3. M15 means the ratio of ingredient in concrete shoud be …
اقرأ أكثرIntroduction of Cost of Concrete Per Cubic Meter
To calculate the concrete rate per 1 m 3, consider a concrete mix of M 20. The ratio of M20 grade concrete is (1:1.5:3) where 1 is a part of cement,1.5 is the part of fine aggregate and 3 is the part of coarse aggregate.
اقرأ أكثرCOST ANALYSIS AND COMPARISON OF RCC RETAINING …
The analysis and estimation of retaining walls using geogrid are the ... Description Unit Rate (Rs. / Unit) Quantity Amount (Rs) Earth Work Excavation cum. 152.5 9 1372.5 ... 1299 5 6495 Back Filling (murum) in Reinforced Zone cum 200 33 6600 Geogrid Sq m. 140 48 6720 Total 21736.19 (Table 2 Cost Analysis of Geogrid Retaining Wall of 6m height)
اقرأ أكثرMaterial estimation for M25 grade concrete. / Estimation …
calculating the quantity of cement, sand, aggregates in M25 grade concrete, estimate of M25 grade concrete, how much material in 1:1:2 mix concrete. ... Let us consider 1 CUM of M25 grade concrete for the calculation purpose. ... Quantity estimate (39) Rate analysis and cost (35) Structural design (19) Surveying (33) Terms and …
اقرأ أكثرWhat is the RCC column cost per sq ft in India
1)what is concrete and its types and properties. 2) concrete quantity calculation for staircase and its formula. Conclusions:-. In india, the typical cost of pillar or reinforced concrete column (RCC column) for one square feet (1 sq ft)) is about Rs. 470. Therefore, RCC column costs about 470 rupees per sq ft.
اقرأ أكثرRate analysis for Concrete- Step by Step calculation with …
Step -1 Write all the known values of the materials. Here we should know that, Total Concrete = 10 m3. M15 means the ratio of ingredient in concrete shoud be (Cement:Sand:Aggregate) = (1:2:4) Density of cement = 1440 kg/m3. Density of steel reinforcement = 7850 kg/m3. Step -2 Calculate dry volume of concrete.
اقرأ أكثرRate Analysis for Concrete
Data required for RCC Rate Analysis. Step 1: Estimation of Materials. Principal Components are: cement, sand, coarse aggregate & steel. Let mix design is M20 …
اقرأ أكثرWhat will be the construction cost of a RCC column?/ …
The material cost of M20 grade concrete = INR 6065.42/ CUM. ( M20 cost is taken from the above-mentioned article.) The material cost of column concrete = [vol. of concrete in CUM × rate/ CUM] = [0.207 × 6065.42/-] = INR 1255.54/-2. Steel: Let us consider the reinforcement in the column as shown in the below-given drawing.
اقرأ أكثرCement Concrete Calculator | PCC Calculator | RCC …
Strength of RCC is defined as compressive strength after 28 days, expressed as M15, M20, where M stands for Mix and 15 stands for 15 N/mm 2 (n/mm 2 must be read as 'Newton's per millimeter Cubed) compressive strength at 28 days. The proportions of materials (cement, sand, coarse aggregate) for nominal mix/design mix concrete that are normally …
اقرأ أكثرReinforced Concrete Quantity and Rate Analysis
March 5, 2017 TeamCivil Construction. In order to perform rate analysis for reinforced concrete, two steps are involved: 1- Estimation of number of labour and equipment, …
اقرأ أكثرSCHEDULE OF RATES
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1,575.00 P&M-046 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 km 73.00 P&M-047 Tipper - 5 cum Transportation of soil, GSB, WMM, Hotmix etc. Capacity in cum 5.5 tonne.km 10.50 P&M-048 Tipper - 5 cum Transportation of soil, GSB, WMM, …
اقرأ أكثرRate Analysis of PCC : (Plain Cement Concrete)
100 to 150mm thick PCC only Labour: Rs.6.00/Sqft. Plum Concrete Only Labour: Rs.8.50-9.00/Cuft That is 300/Cum. Cement Bag: Rs.50- 60/Bag. Shuttering With Material: Rs.450-550/ Sqm. All above Rates is current market rate and analysis are considered as per Mix design report.
اقرأ أكثرRate analysis of brickwork
10m2 brickwork cost = INR 7384, so rate and cost per sq meter of brickwork = 7384/10= 738.4 = INR 740. Rate per square metre for brickwork is INR 740. conclusion :- 1) Rate per cum for brickwork is INR 7384 & 2) Rate per sq m for brickwork is INR 740. And rate per cubic metre for brickwork is varying between INR 6000 to 8500 according to their ...
اقرأ أكثرHow to Calculate Rate Analysis For Concrete 1:2:4?
How to Calculate Rate Analysis For Concrete 1:2:4? - 1. ... Sand = 0.22 x 2 = 0.44 cum. Aggregate = 0.22 x 4 = 0.88 cum. ... Which is the code used for the design of the RCC Bridge? 1 Answer; What is the tolerance for compression test results of concrete, according to the standards?
اقرأ أكثرReinforced Concrete Quantity and Rate Analysis
March 5, 2017 TeamCivil Construction. In order to perform rate analysis for reinforced concrete, two steps are involved: 1- Estimation of number of labour and equipment, quantity of materials, miscellaneous items required for for a certain quantity of reinforced concrete. 2- Determination of structural element for which the rate analysis is needed.
اقرأ أكثرHow to calculate the labor cost for RCC columns?/ Labor rate …
👀. What will be the construction cost of a 3m. height RCC column? 1. Column concreting: The labor rate of column concreting will be between INR 600/- to 1000/- per CUM. Let us take the average rate of INR 800/- per CUM. The labor cost of column concreting = [total vol. of concrete in CUM × rate/CUM.] =[0.207 CUM × 800/-] = INR …
اقرأ أكثرHow to calculate the cost of plinth beams for a building?/ …
The material cost of M20 grade concrete = INR 6065.42/ CUM. ( M20 cost is taken from the above-mentioned article.) The material cost of plinth beam concrete = [vol. of concrete in CUM × rate/ CUM] = [1.677 × 6065.42/-] = INR 10,171.70/-2. Steel: Let us consider 1.75% of steel reinforcement to the total vol. of concrete.
اقرأ أكثر3. Rate Analysis for RCC in 1:1.5:3 (1:1:2)
Rate Analysis for RCC in 1:1.5:3 Rate Analysis for RCC in 1:1.5;3 is as follows. Rate Analysis for RCC in 1:1:2 ... For 10 cum:15.20cum 15.20/(Sum of Proportion) Therefore, 15.20cum/(1+1+2) Therefore, Value for 0ne (1) is ... Rate Analysis Estimate, Rate analysis, Rate Analysis for RCC Post navigation. 2. Rate Analysis for PCC
اقرأ أكثرHow to calculate the labor cost for RCC footings?/ Labor rate for the
Calculating the construction cost of RCC footing. 1. Footing concreting: The labor rate of footing concreting will be between INR 500/- to 900/- per CUM. Let us take the average rate of INR 700/- per CUM. The labor cost for the concreting of footing = [total vol. of concrete in CUM × rate/CUM.] =[0.9 CUM × 700/-] = INR 630/-
اقرأ أكثرHow to Calculate Rate Analysis For Concrete 1:2:4?
How to Calculate Rate Analysis For Concrete 1:2:4? - 1. ... Sand = 0.22 x 2 = 0.44 cum. Aggregate = 0.22 x 4 = 0.88 cum. ... Which is the code used for the design …
اقرأ أكثرWhat will be the cost of M25 grade concrete ?/How to …
/ Estimation of cement, sand, & aggregates in M25 ( 1:1:2 mix ratio) concrete. A. Material cost: The average ongoing market rate in India is considered for calculation purposes. B. Labor cost : The labor rate for concrete ranges from INR 1000/- to 1600/- per CUM. Let us take the average rate of INR 1300/ - for calculation purposes.
اقرأ أكثرWhat will be the cost of RCC pad footing?/ Calculating the …
The material cost of M20 grade concrete = INR 6065.42/ CUM. ( M20 cost is taken from the above-mentioned article.) The material cost of footing concrete = [vol. of concrete in CUM × rate/ CUM] = [0.9 × 6065.42/-] = INR 5458.88/-2. Steel: Let us consider the reinforcement in the footing as shown in the below-given drawing.
اقرأ أكثرCalculating the construction cost of a compound wall/ …
The volume of RCC for compound wall = [for footings+ for plinth beam + for columns] = [0.743 cum + 2.75 cum. +1.561 cum.] = 5.054 cum.i.e. 178.48 cu ft. Let us make this RCC in M20-grade concrete. The no. of cement bags required for RCC work = [8.06 bags ×( 5.054 cum ÷ 1 cum )] = 40.73 bags. The volume of sand required for RCC …
اقرأ أكثرRate Analysis of RCC (Reinforcement Cement …
This quantity estimation of RCC is required for the rate analysis. ... (Reinforced Concrete Cement) wall construction involves determining the costs …
اقرأ أكثرEstimation of Water Tank | RCC Water Tank Estimate
Deduction for hole = π (0.6) 2 /4 * 0.1 = 0.0282 m 3 RCC work in Slab – Deduction for hole = 1.423 m 3 = net quantity of RCC slab ... Download the excel sheet to make analysis of Rates of Building Construction In what way to use Excel Sheet for Making Estimation of a Building; RCC Box Culvert Bar Bending Schedule; Download Quantity Takeoff ...
اقرأ أكثر